A major design change to work at the 19 Mile slide will add up to $2 million to the cost of the Haines Highway reconstruction project and may delay a final layer of paving until next year, according to officials with the state Department of Transportation.
The modifications include adding reinforced concrete, steel reinforcing bar, and crushed rock to massive abutments intended to channel mountainside debris into five garage-size culverts to be placed beneath the…